107.12 MW PV Project + 153 MW BESS 

 Romania

Code project: IEA01


Sale Process Details

Percentage on Sale: 100% - 100%

Deal Type: Permitting in progress

Process Comments: The Project offers a compelling opportunity to acquire a hybrid project comprising 107.12 MWp of PV and 153 MW of BESS, located in central Romania.


The project is already at an advanced stage of development and is expected to reach full RtB status by the second quarter of 2027, while COD is anticipated in the fourth quarter of 2027.


The seller is seeking an investment partner or an investor to acquire 100% of the Project and is open to receiving Expressions of Interest.


Express your interest through PVLAND to connect with the seller of Project.

About the Seller

The seller is a Romanian renewable energy developer with extensive experience in the execution of large-scale wind, solar photovoltaic, and energy storage projects.


The company manages a robust portfolio comprising multiple solar photovoltaic and hybrid projects in one of Europe’s key markets. Its pipeline in the country includes utility-scale solar developments alongside significant battery energy storage capacity (BESS), reflecting a strong positioning in high-growth and high-demand segments.


With a clear focus on technological innovation and sustainable value creation, the seller applies rigorous environmental, technical, and engineering standards across all its projects. Furthermore, it remains open to establishing long-term strategic partnerships aimed at supporting the continuous expansion and strengthening of its renewable energy platform.

General Information

Technology: Solar PV, BESS

Total Installed Capacity PV: 107.12 MWp

Total Installed Capacity PV: 153 MWp

Location: Romania

Other Details: This project is already at an advanced development stage, expecting full RtB by Q2 2027, and COD targeted for Q4 2027.

Solar PV Details & Design

Installed Capacity: 107.12 MWp

Annual irradiation (kWh/m²): 1498.1 kWh/m²

Development Status: Permitting in progress

Ready to Build (RtB) Date: Q2 2027

Commercial Operation Date (COD): Q4 2027

Panel Configuration: 2V

Module Power: 650Wp

Type of Structure: Fixed mounting structure

Module Type: JKM-650N-66HL4-BDV 650Wp

Other Comments: No information is available at this stage.

BESS Details & Design
BESS Details & Design

Installed Capacity: 153 MW

Hours Cycles: 4 h

Development Status: Permitting in progress

Ready to Build (RtB) Date: Q2 2027

Commercial Operation Date (COD): Q4 2028

Injection Capacity: 153 MW

Consumption Capacity: 15 MW

BESS - Energy storage capacity (MWh): 612 MWh

Storage Technology: Lithium Iron Phosphate (LFP) Battery

Permitting

Connection Permit: Q2 2027

STMG Acceptance: Obtained (Q2 2027)

Environmental Permit (EIA): Obtained (Q3 2026)

Autorizzazione Unica (AU): Pending (Q2 2027)

Connection Infrastructure

Evacuation line voltage: 110 kV

Connection type: Underground

Connection to: Substation

Grid Conditions Costs: No information is available at this stage.

Connection Costs Comments: No information is available at this stage.

Shared Infrastructure: No information is available at this stage.

Other Connection Infrastructure Comments: No information is available at this stage.

Land Rights

Land Surface: 110 ha

Land Types: Rental

Land Price: 2.200 €/ha/year

Land Contracted Percentage: 100 %

Land Comments: Additional information regarding the land will be disclosed in the next phase.

Expropriation Status: Not required

Expropriation Comments: Not required.

Capex & Opex

Estimated EPC: No information is available at this stage.

EPC comments: No information is available at this stage.

O&M Comments: No information is available at this stage.

Other Comments: No information is available at this stage.

Other Information

Energy offset: Merchant

Energy offset Details: The project is targeting the execution of a 5-year Power Purchase Agreement (PPA). Alternatively, the generated electricity may be commercialized through OPCOM (Romania’s electricity market operator), with access to both the Day-Ahead Market (DAM) and Intraday Market (IDM).

The integration of a Battery Energy Storage System (BESS) significantly enhances the project’s commercial strategy by enabling revenue optimization through energy shifting and price arbitrage. The storage system allows the project to dispatch electricity during peak pricing periods, actively participate in intraday markets, and manage market volatility more effectively.

This hybrid configuration provides increased flexibility, supports merchant exposure strategies, and enhances overall revenue stability and bankability, making the project particularly attractive to institutional investors and infrastructure funds seeking optimized risk-adjusted returns.

Financial details: There is no debt in place for this project.

Other Comments: Further info will be shared in the following phase.